Spent Naval fuel unlikely to be shipped this year

Publish date: October 17, 1997

Written by: Igor Kudrik

The shipment of spent nuclear fuel from Murmansk and Arkhangel'sk counties for reprocessing at Mayak, planned for this Autumn, has been postponed. Among the reasons are lacks of both funding and technical means to perform the operation.

On May 21 the special train for shipment of spent nuclear fuel finally arrived at Severodvinsk. The train was scheduled to arrive at April 2, but was delayed due to technical malfunctions. This was the only shipment of spent nuclear fuel from the region performed in 1997.

In the end of September there was a special meeting of Severodvinsk city council, aimed at defining milestones in solving the problem with spent fuel shipments. The situation has not changed at all since the last shipment operation: The two service vessels assisting at subs defuelling operations and loading of spent fuel into the train are still unservicable. The PM-124 (pr. 326M), which entered service 37 years ago, has to be decommissioned; while the second vessel, the PM-63 (pr. 2020), will be granted permission to perform defuelling operations only after overhaul repairs. These repairs will cost almost 7 million USD. The money is not available, although promised by the state.

Meanwhile, more than 30 reactor cores are concentrated in Severodvinsk, inside the reactors of laid-up submarines awaiting their turn to be decommissioned.

A similar situation has developed at the ice-breaker base Atomflot in Murmansk – the second loading point for spent nuclear fuel from Northern Fleet vessels and the civilian nuclear-powered ice-breakers of Murmansk Shipping Company (MSC). Atomflot has the necessary facilities to perform the operations, but the delayed funding hampers the process. The special train is scheduled to arrive here by October-November, but the nuclear safety department of MSC has little faith in this schedule.

The whole situation is aggravated by the fact that since March 1997 Mayak reprocessing plant has been deprived of its licence to reprocess spent fuel by the Russian State Nuclear Safety Inspection (GAN). Neither GAN’s nor Mayak’s officials are willing to suggest when the reprocessing activities may be resumed.

As for now, according to the Naval experts, there must be at least 10 spent fuel shipments a year from the region to stabilise the situation.

More News

All news

The role of CCS in Germany’s climate toolbox: Bellona Deutschland’s statement in the Association Hearing

After years of inaction, Germany is working on its Carbon Management Strategy to resolve how CCS can play a role in climate action in industry. At the end of February, the Federal Ministry for Economic Affairs and Climate Action published first key points and a proposal to amend the law Kohlenstoffdioxid Speicherungsgesetz (KSpG). Bellona Deutschland, who was actively involved in the previous stakeholder dialogue submitted a statement in the association hearing.

Project LNG 2.

Bellona’s new working paper analyzes Russia’s big LNG ambitions the Arctic

In the midst of a global discussion on whether natural gas should be used as a transitional fuel and whether emissions from its extraction, production, transport and use are significantly less than those from other fossil fuels, Russia has developed ambitious plans to increase its own production of liquified natural gas (LNG) in the Arctic – a region with 75% of proven gas reserves in Russia – to raise its share in the international gas trade.